Westshore - Potash Storage Building
Client: Westshore Terminals Limited Partnership
Location: Delta, BC
Value: $15,510,000
Completed: April 2024
Project Synopsis:
- Supply, placement, relocation, and removal of preload material for the future Potash Storage Building (PSB) at Westshore Terminals in Delta, BC
- The contract includes the supply and placement of compacted general fill and preload to support the first phase of PSB construction. Preloading will be completed in two stages—Phase 1, Stage 1 and Phase 1, Stage 2—each constructed over approximately three months, followed by settlement periods of three to nine months depending on settlement rates. The scope also includes proof rolling, installation and removal of settlement monitoring pins and instruments, and ongoing settlement monitoring surveys throughout construction.